Reporting snapshot · 26 November 2026 (Asia/Karachi). The committee ordered to audit the technology parks has no published membership, terms of reference or completion date, no list of the 86 cities has been released, and the export and training figures came from a ministry briefing rather than a published dataset. The meeting was held behind closed doors.
On Wednesday, 25 November, Prime Minister Shehbaz Sharif chaired a review of the Ministry of Information Technology and Telecommunication in Islamabad and ordered an independent, third-party audit of every technology park now operating under the Special Technology Zones Authority, together with a review of the law that governs how those zones are used. Radio Pakistan’s readout of the meeting records two directions: a committee is to be formed to carry out the audit, and officials are to examine the statute so that provisions allowing technology companies to be established in the zones cannot be misused. Pakistan Today reported the orders on 26 November, and The Express Tribune carried the same briefing in a report published the same morning.
The order is directed at the parks themselves rather than at the projects inside them, and it comes after the prime minister set a deadline for the Alibaba-backed digitisation work in October, when ministries were told to complete every Alibaba measure by November and report back — a schedule KhabarWire covered when it was given. The 25 November review was the follow-through meeting on that file, and the audit is the one direction in it with consequences for companies already operating inside the zones.
Officials told the meeting that 32 technology zones are being built under seven clusters nationwide, that 21 are operational and 11 are still under construction, and that around 300 technology companies have set up offices in them. The zones have attracted Rs100 billion of realised investment, with proposals worth a further Rs105 billion under consideration, Pakistan Today reported. The same briefing put IT services exports at $4.6 billion by June 2026, the end of the last financial year, with a further $1.24 billion recorded in the July–September quarter, freelance exports at $1.165 billion by June 2026, and more than 931,000 people trained under the DigiSkills programme by June 2026.
On the telecom side, officials described progress towards the launch of 5G services as satisfactory and said telecom operators had completed network upgrades in 86 cities, alongside improving 4G coverage, broadband speeds and smartphone penetration. Shehbaz directed the authorities to improve internet speeds and connectivity, and to accelerate training that matches the requirements of the global labour market.
What the audit order actually covers
Two things were ordered, and both are open-ended. The audit is to be carried out by a committee that has not been named, with no terms of reference and no completion date published. The law review has no timetable either, and nothing further about either direction has been published since the meeting.
The order to look at the law is the sharper of the two, because the registration route it governs is the one on which the zones’ occupancy depends. The government says 21 zones are running with offices of around 300 technology companies and Rs100 billion of realised investment, and that another Rs105 billion of proposals is waiting on decisions. If the corporate registration provisions are being used for something other than the technology business they were written for, an audit and a legal review are the two instruments the government has chosen to find out.
What the order does not do is say what happens to a tenant company whose registration is later found to be improper, or whether the audit reaches the eleven zones still under construction, where the pipeline investment sits.
Network upgrades in 86 cities, and what is actually live
The briefing’s phrase is network upgrades completed in 86 cities, and the distance between that and a commercial 5G service in 86 cities is the distance between groundwork and a launch. The regulator that licenses the service, the Pakistan Telecommunication Authority, authorised Jazz, Ufone and Zong to begin 5G in phases on 19 March 2026 and told them to publish lists of the areas where service is live and the handsets that support it, the authority said at the time. All three have since brought 5G to paying customers, and KhabarWire’s report on the auction that paid for it set out the bands each operator won.
The scale of what has been built is measurable, and it is smaller than a service in 86 cities. Opensignal, which measures networks from real devices, counted 1,782 5G sites across 24 cities as of October 2026 and found that 5G users spent 6.4 per cent of their time connected to 5G in September, in its November analysis. Its data shows deployments resting on the 2.6GHz band alone, roughly 15 per cent of cell sites on fibre backhaul, and fewer than one per cent of handsets in the country able to use 5G.
None of that contradicts the briefing. An upgraded network is a precondition for service, and the government was told about upgrades. It does mean that the launch of 5G services in the readout describes a rollout already under way in two dozen cities rather than an event still to come, and that no list of the 86 cities has been published, so the number cannot be checked against any site count. For a reader with a phone, the practical question is whether a handset bought today reaches a 5G signal, and the measured answer is that most connected time is still spent on 4G.
The government super app Alibaba is building
Under the Strategic Transformative Framework, the partnership Pakistan signed with the Chinese e-commerce group, officials said Alibaba is developing a single super app for the government that would put public-facing services on one digital platform. It is the first time this meeting has named that product. The October order covered the other Alibaba projects — an artificial-intelligence cancer diagnosis pilot, Ignite training for IT graduates, analytics for the oil and gas regulator, digital verification of trade documents — and set a November deadline for them. What this briefing adds is a platform rather than another list of schemes.
What the readout does not say matters as much as what it does. There is no launch date, no list of the services that would move onto the platform, no statement about whether existing citizen apps would be folded into it, and no detail on where citizens’ data would be held or how it would be protected. The earlier directives in this file came without published implementation plans, and so has this one. The Technology and AI file follows the wider programme.
The export figures, and what they leave out
The $4.6 billion covers the financial year that ended in June 2026, and the $1.24 billion for July to September 2026 is the first quarter of the year now under way. The two are on different bases and should not be treated as one series. The monthly figures KhabarWire reported on 18 November — a record $453 million in October and $1.73 billion across the first four months of the year — come from a brokerage compilation of remittance data rather than the ministry’s own accounting, and neither set of numbers has been published with a breakdown by service line or destination.
The DigiSkills number is a training count rather than an employment count. 931,000 people had completed the programme by June 2026, with training continuing from July to October against annual targets; the briefing did not say how many of those trainees are in work, or what the targets are.
What is not settled is as consequential as the order itself. The audit committee has no named members, no published terms of reference and no deadline, and the law review has no timetable. No 5G launch date, no city list and no super app schedule have been published either. What can be watched is whether the committee is formed quickly, whether the government names the 86 cities, and whether the audit reaches the eleven zones still under construction and the Rs105 billion of investment proposals that have not yet been counted.